HOME IMPROVEMENT Index
Appliances
Basement
Bathrooms
Bedrooms
Cleaning
Contractors
Doors
Driveways & Paths
Duct Tape
Electrical Systems
Family Room
Fences & Gates
Fireplace
Floor Coverings
Furniture
Handles, Knobs & Hinges
Help on the Homefront
Home Energy Efficiency
Home Office
Homeowner in Process
House Exterior
Indoor Pests
Kitchens
Lighting
Outdoor Equipment
Outdoor Structures
Trellises & Arbors
Decks
Log Cabins
Maintenance
Other

Painting
Plumbing
Safety
Sports-Related Additions
Staining
Stairs
Storage
Tools
Utility Room
Walls & Ceilings
Windows

BEST OF
HOME IMPROVEMENT
Flooring
Decks
Mold Quiz
Home Safety
Tiling Techniques
Lighting Solutions
Weekend Projects
DIY to the Rescue
Home Renovations
Bathroom Makeover
Kitchen Renovations
Ultimate Media Room
Be Your Own Contractor

SPONSOR LINKS

  • Sliding House
  • DIY's Finders Fixers team comes to the rescue of a couple with a sliding yard, deck and house.
    From "Finders Fixers"
    episode DFFX-205


    What can be done when a house, deck and yard are sliding? DIY's Wally Conway, one of Finders Fixers' home inspectors, takes charge by backfilling under the deck, securing the deck posts and building a new bulkhead.

    advertisement


    PHOTO

    Soil erosion took its toll on Larry and Cathlene Gancars's backyard...
    PHOTO

    ...before Wally Conway and his DIY team took care of the problem with backfill and post support.
    PHOTO

    Figure A
    PHOTO

    Figure B
    Fix #1: Backfill Under the Deck and Secure the Posts

    Materials:

    dirt and backfill (as needed)
    hammer
    nails
    rubber mallet
    wheelbarrow
    garden hose
    saw
    builder's plastic
    tape
    scissors

    1. Rather than shoveling the backfill underneath the deck, it would be easier to load the dirt in from the top. Begin by removing the deck boards from the area where the backfill is needed.

    2. Once the boards are out of the way, begin loading in the dirt one wheelbarrow at a time. Make sure the dirt reaches the level of the original footer and goes all the way to the top of the retaining wall.

    3. Use a garden hose to water down the backfill. This will help settle out any air pockets and compact the soil.

    4. Repeat this process underneath the entire back deck of the house.

    5. To secure the posts, first remove the existing post. Cut the post with a saw and knock it out using a mallet.

    6. Put the new footer and post in place (figure A). Using a drill, secure the post in place with bolts. Finish the post by staining it to match the rest of the deck.

    7. To help shed water away from the house and prevent future problems with erosion, lay down a plastic cover. Spread the builder's plastic over the desired area.

    8. Tack the edge of the plastic using a furring strip (figure B). Once in place, slit the sheet at every post so that the plastic cover acts like a skirt. Then re-tape the seams.

    9. Once the plastic cover is in place, replace the deck boards and drill back into place.

    PHOTO

    A new bulkhead is built to keep the slide at bay.
    PHOTO

    Figure C
    PHOTO

    Figure D
    PHOTO

    Figure E
    Fix #2: Build New Bulkhead

    Materials:

    rubber mallet
    shovel
    4 x 4 posts
    pressure treated wood boards
    saw
    concrete mix
    drill
    cable tie backs
    stainless eyebolts
    washers
    wheelbarrow
    backfill

    1. Remove any of the existing rotted boards using a mallet to knock them out of place.

    2. Dig holes (figure C) for the new 4 x 4 posts.

    3. Cut the ends of the posts to create stakes and then place one at each hole.

    4. Mix the batch of concrete following the manufacturer's instructions. Set the posts in the holds by pouring the cement into the base.

    5. While the cement gets a chance to set, prepare the boards for the new bulkhead. Paint a coat of preservative wood sealant onto each of the boards. Apply liberally and allow it to soak into the wood. This will extend the life of the wooden boards.

    6. As the boards dry, use a level and chalk line to mark where the new boards should be secured to the posts.

    7. Prepare the tieback posts. Drill a hole, insert the cables (figure D) and secure loosely with stainless eyebolts and the washers. The tiebacks will be tightened once the posts are in place.

      Note: Consult a professional to determine the proper placement of each tieback post in your backyard.

    8. Once the tiebacks are prepared (figure E), the wooden boards have dried, and the cement base of each post has set, you may proceed in constructing the bulkhead structure. Install and secure each of the treated boards to the posts.

    9. Once the entire wall is complete, lay down a filter screen at the bottom of the trench created by the old and new wall. Then lay down a corrugated drainpipe on top of the filter and run it along the entire base of the trench. The filter and drainpipe will allow any excess groundwater to channel safely at either end of the wall.

    10. To complete the bulkhead, grab your wheelbarrow and backfill the trench.